Energizing and putting into operation VINFAST substation - 110kV Dong Bai Substation

On October 21 2018, Hai Phong Eletraco - HPE coordinated with VietNam PRP successfully energized Dong Bai 110 kV Substation, supply to Vinfast Automotive Factory.

fdda3f606dbc8de2d4ad

At 17h35 on October 21, 2018, HPE commissioned and successfully energized Dong Bai110 kV Substation and branches.

0214e80707d9e787bec8
Pic: Dong Bai 110 kV Substation.

Construction of the Project “Dong Bai 110 kV Substation” has started since August 2018. In phase 1, Dong Bai 110 kV Substation has been constructed with one 110/22kV transformer, with a capacity of 63MVA. In phase 2 and phase 3, substation capacities up to 3x63MVA. The project has been put into operation on schedule, meeting quality requirements, contributing to securing stable and reliable electricity supply to VINFAST Automotive Factory - the factory under construction will be able to produce 250,000 vehicles a year - equal to current annual car sales in Vietnam.

44396185 1888238597908183 4010475310922334208 oPic:VINFAST Automotive Factory

VietNam PRP has supported HPE in Relay settings calculation and relay settings table, Operational coordination procedure of substation and Energzing process, to ensure substation energize in schedule.

Mr. Binh Bui Tien –Director of Hai Phong Electraco, representative of the main organization responsible for management and operation of Dong Bai 110 kV Substation says that the company has prepared adequately manpower, tools and instruments to take over and operate the Substation, and send many thanks to VietNam PRP for support of the company during the Energzing process.


3f1fc3804d53ad0df442

Pic: Mr Giang Do Truong, CEO of VietNam PRP and HPE leadership team. 

Tag: Dong Bai Substation, Vinfast, PRP

 

 

Customer feedback

Electricity Regulatory Authority of Vietnam

ERAV

"These projects finished and we satisfied with the results. PRP brought us the sufficient and easy-to-use transmission charges calculation model. The IT system and ERAV’s website met our requirement and the training for ERAV’s staffing using the IT system and website was undertaken carefully"

 Thang Long JSC.

TLP "The Grid Impact study was prepared thoroughly and defended successfully. The SCADA and metering system was designed professionally and adequately. We feel pleased with the results PRP brought to us."

 AES Transpower

AES "The study and two supplementary reports was conducted comprehensively and carefully, with accurate computation and precise assessment. We are looking forward to cooperate with PRP in future."

 PV Nhon Trach 2 JSC.

PV NT2 "PRP is an experienced Consultant Company in preparing the Grid Impact Study; we choose them as the perfect Consultant to do it and PRP did not disappointed us."

 


mod_vvisit_countermod_vvisit_countermod_vvisit_countermod_vvisit_countermod_vvisit_countermod_vvisit_counter
mod_vvisit_counterToday81
mod_vvisit_counterYesterday144
mod_vvisit_counterThis week1110
mod_vvisit_counterLast week1336
mod_vvisit_counterThis Month4512
mod_vvisit_counterLast Month4518
mod_vvisit_counterAll days333934

Online (20 minutes ago): 3
Your IP: 3.237.71.23
,
Today: 27 Sep, 2020

Sponsored Links


JoomlaWatch Stats 1.2.9 by Matej Koval